Nam Ao-Nam Pot Hydropower Info by Hobo Maps - Go to Hydropower Projects Web Page - - - HOME
The Nam Ao-Nam Pot Hydropower project is located near the junction of the Nam Pot and Nam Siam (rivers) near Ban Pha village, Phaxay or Kham District, Xieng Khouang Province, northern Lao PDR.
The project is sometimes referred to as the Nam Ao (Nam Aow) project and in older times as the Nam Pot project - we combine both names for reference as does ADB & JICA.
Nam Ao-Nam Pot Dam and Reservoir location coordinates - 19°09'39.0"N 103°17'01.0"E (19.160833, 103.283611) - on satellite image below:
Nam Pot river is a tributary of the Nam Siam that merges into the Nam Ngiep which joins the Mekong River near Paksan, Laos.
We are guessing where the Nam Ao river might be in the image below.
Also guessing that the construction activity below is for a future new dam and reservoir at coordinates 19°09'18.7"N 103°15'58.9"E (19.155180, 103.266356).
Nam Ao-Nam Pot Dam & Reservoir satellite image below:
The project was studied by Knight Piesold in 1997. A development mandate was awarded to VKS of India but the project became inactive and was cancelled.
A Lao-based entity Bothong Inter Company Ltd. took over the US$ 30 million project and started construction in October 2015. The project was delayed in 2017 by a flooding accident. The Project was said to be at 85% completion at the time of the flood.
The project is being undertaken by a privately-owned company and managed by local investors.
Electricity generated is planned to be sold to Electricite du Laos (EDL).
The dam structure and reservoir are located 3.5 km upstream from the joining of the Nam Pot river with the Nam Siam river. Downstream of the dam and reservoir, the Nam Pot falls 700 meters in elevation to the powerhouse.
Upstream of the dam the Nam Pot river flows in a shallow wide channel. The area inundated by the reservoir is to be mainly in a narrow valley.
This project has 15 MW installed capacity with about 700 meters head.
Nam Ao-Nam Pot powerhouse location coordinates - 19°08'15.0"N 103°17'17.0"E (19.137500, 103.288056) - on satellite images below:
Reservoir surface full supply level is to be at 1,140 meters above sea level while minimum operating level is at 1,127 meters above sea level.
Nam Ao-Nam Pot hydropower project layout image below:
Nam Ao-Nam Pot & Nam Ngiep 2 area maps below shows both powerhouses only 2.5 km distance apart on the Nam Siam river:
On Sept. 11, 2017 while under construction and during heavy rains, a Nam Ao-Nam Pot subsidiary dam broke and floodwaters flowed into the powerhouse construction site doing extensive damage. The flood also caused damage to the downriver Nam Ngiep 2 hydropower project and to National Road 1D causing its temporary closure. 8 villages and agricultural lands were also flooded.
Image below and video of the flood near the construction site can be seen.
Nam Ao-Nam Pot Hyropower project planning details below from a 2004 preliminary study document that is no longer reliable.