September 29, 2025 during typhoon Buoalai we have reports of a "Dam Failure" at Nam Ngiep 2B with comment of "big loss" but few details. See Facebook link 1 & Facebook link 2 . On one video we can see the dam structure with all 4 release gates closed and water rushing around one end of the structure which seems to be some sort of a washout. Apparently no injuries or casualties but some roads (Road 1D?) were closed temporarily.
Images below after the failure:




Nam Ngiep 2B hydropower project is part of Nam Ngiep 2ABC Hydropower project (2A, 2B & 2C). Lao-based Nonghai Group Co. Ltd. is developing several hydropower sites in northern Lao PDR southeast of the Plain of Jars area and another in Kham District.
Nam Ngiep is pronounced like "Nam Nyiep".
The project is located in Khoun District of Xaysomboun Province, Lao PDR.
Images below show Nam Ngiep 2B hydropower powerhouse site at coordinates - 19°09'27.4"N 103°20'54.1"E (19.157611, 103.348361).


Nam Ngiep 2B dam site images below at coordinates - 19°11'11.7"N 103°21'22.4"E (19.186583, 103.356222) - from before the flooding and damage in Oct. 2025.


The engineering, procurement and construction (EPC) contractor for Nam Ngiep 2B project was Chongqing Water Turbine Works Co., Ltd (CWTW) from China.
The project installed capacity is 18 MW from 3 horizontal axis Francis turbine-generator sets of 6 MW each with annual output potential of 76 GWh.
The project was finished and commissioned on 31 January 2018 and is currently in operation.
The dam structure is constructed of reinforced concrete with drainage gates.
The project water catchment area is 878 square kilometers. The reservoir capacity on the Nam Ngiep river above the dam is only 123,000 cubic meters.
Non-pressure tunnel of Nam Ngiep 2B HHP was constructed by Zheng Hong Company.
Nam Ngiep 2B site image below:

see short video of high water at plant in July 2025

Nam Ngiep 2A, 2B & 2C partial layouts image below:

Images below of Nam Ngiep 2B penstock and plant during construction



Images below of Nam Ngiep 2B plant and switch yard during construction



Images below of dam structure for Nam Ngiep 2B project




Images below of Nam Ngiep 2B powerhouse interior








Nam Ngiep Dams location shown in map below:

Click to see our other web pages for Nam Ngiep 2A and Nam Ngiep 2C.
Satellite image map below for Nam Ngiep 2 2A, 2B & 2C hydropower projects:


Satellite image map below for Nam Ngiep River Basin hydropower projects:

Click HERE to see our hydropower web page for the greater Nam Ngiep catchment basin which describes the various dams, reservoirs and diversion projects in the drainage basin that are often inter-connected.